hit counter script
ABB RET670 Commissioning Manual

ABB RET670 Commissioning Manual

Relion 670 series, transformer protection
Hide thumbs Also See for RET670:
Table of Contents

Advertisement

R E L I O N ® 670 SERIES
Transformer protection RET670
Version 2.2 IEC
Commissioning manual

Advertisement

Table of Contents
loading

Summary of Contents for ABB RET670

  • Page 1 — R E L I O N ® 670 SERIES Transformer protection RET670 Version 2.2 IEC Commissioning manual...
  • Page 3 Document ID: 1MRK 504 165-UEN Issued: October 2017 Revision: A Product version: 2.2.1 © Copyright 2017 ABB. All rights reserved...
  • Page 4 Copyright This document and parts thereof must not be reproduced or copied without written permission from ABB, and the contents thereof must not be imparted to a third party, nor used for any unauthorized purpose. The software and hardware described in this document is furnished under a license and may be used or disclosed only in accordance with the terms of such license.
  • Page 5 In case any errors are detected, the reader is kindly requested to notify the manufacturer. Other than under explicit contractual commitments, in no event shall ABB be responsible or liable for any loss or damage resulting from the use of this manual or the application of the equipment.
  • Page 6 (EMC Directive 2004/108/EC) and concerning electrical equipment for use within specified voltage limits (Low-voltage directive 2006/95/EC). This conformity is the result of tests conducted by ABB in accordance with the product standard EN 60255-26 for the EMC directive, and with the product standards EN 60255-1 and EN 60255-27 for the low voltage directive.
  • Page 7: Table Of Contents

    Setting up communication between PCM600 and the IED....49 Writing an application configuration to the IED.........54 Checking CT circuits.................55 Checking VT circuits.................56 Using the RTXP test switch.............. 56 Checking the binary input/output circuits..........57 Binary input circuits..............57 Binary output circuits..............57 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 8 Verifying the communication............78 Verifying the IEEE C37.118/1344 TCP communication....79 Verifying the IEEE C37.118/1344 UDP communication....85 Optical budget calculation for PMU - PDC communication....86 Section 10 Testing IED operation.............87 Preparing for test................87 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 9 Restricted earth fault protection, low impedance REFPDIF ..107 Verifying the settings............107 Completing the test.............. 108 Additional security logic for differential protection LDRGFC ..108 Verifying the settings............108 Completing the test.............. 110 Impedance protection..............110 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 10 Completing the test.............. 141 Power swing logic PSLPSCH............ 141 Testing the carrier send and trip signals......142 Testing the influence of the residual overcurrent protection.142 Checking the underreaching zone........143 Completing the test.............. 143 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 11 EF4PTOC ....... 175 Four step directional earth fault protection......175 Four step non-directional earth fault protection....176 Completing the test.............. 176 Four step negative sequence overcurrent protection NS4PTOC .................176 Completing the test.............. 177 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 12 Negative-sequence time overcurrent protection for machines NS2PTOC ..............199 Verifying settings by secondary injection......199 Completing the test.............. 201 Voltage-restrained time overcurrent protection VRPVOC..201 Verifying the settings............201 Completing the test.............. 205 Voltage protection................205 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 13 Overcurrent feature with current restraint......219 Overcurrent feature with voltage restraint......219 Overcurrent feature with directionality........220 Over/Undervoltage feature........... 220 Completing the test.............. 221 Secondary system supervision............221 Current circuit supervision CCSSPVC........221 Verifying the settings............221 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 14 Scheme communication..............247 Scheme communication logic for distance or overcurrent protection ZCPSCH ..............247 Testing permissive underreaching........248 Testing permissive overreaching..........248 Testing blocking scheme............248 Testing delta blocking scheme..........249 Checking of unblocking logic..........249 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 15 263 Testing the liquid medium supervision for temperature alarm and temperature lock out conditions......264 Completing the test.............. 264 Breaker monitoring SSCBR............264 Verifying the settings............265 Completing the test.............. 266 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 16 Section 13 Checking the directionality........... 283 Overview..................283 Testing the directionality of the distance protection......283 Section 14 Commissioning and maintenance of the fault clearing system............287 Commissioning tests..............287 Periodic maintenance tests............287 Visual inspection................288 Maintenance tests..............288 Preparation................288 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 17 General IED status............... 293 Fault tracing..................294 Internal fault indications.............294 Using front-connected PC............295 Diagnosing the IED status via the LHMI hint menu....297 Repair instruction................299 Repair support................300 Maintenance................... 300 Section 16 Glossary............... 301 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 19: Section 1 Introduction

    The commissioning personnel must have a basic knowledge of handling electronic equipment. The commissioning and maintenance personnel must be well experienced in using protection equipment, test equipment, protection functions and the configured functional logics in the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 20: Product Documentation

    The manual provides procedures for the checking of external circuitry and energizing the IED, parameter setting and configuration as well as verifying settings by secondary injection. The manual Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 21: Document Revision History

    The guideline can be used as a technical reference during the engineering phase, installation and commissioning phase, and during normal service. 1.3.2 Document revision history GUID-C8027F8A-D3CB-41C1-B078-F9E59BB73A6C v4 Document revision/date History –/May 2017 First release Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 22: Related Documents

    GUID-2945B229-DAB0-4F15-8A0E-B9CF0C2C7B15 v12 The electrical warning icon indicates the presence of a hazard which could result in electrical shock. The warning icon indicates the presence of a hazard which could result in personal injury. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 23: Document Conventions

    For example, to save the changes in non-volatile memory, select Yes and press • Parameter names are shown in italics. For example, the function can be enabled and disabled with the Operation setting. • Each function block symbol shows the available input/output signal. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 24: Iec 61850 Edition 1 / Edition 2 Mapping

    SECLLN0 ALMCALH ALMCALH ALMCALH ALTIM ALTIM ALTMS ALTMS ALTRK ALTRK BCZPDIF BCZPDIF BCZPDIF BCZSPDIF BCZSPDIF BCZSPDIF BCZTPDIF BCZTPDIF BCZTPDIF BDCGAPC SWSGGIO BBCSWI BDCGAPC BDZSGAPC BBS6LLN0 LLN0 BDZSGAPC BDZSGAPC Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 25 BRPTOC BRPTOC BRPTOC BTIGAPC B16IFCVI BTIGAPC BUSPTRC_B1 BUSPTRC BUSPTRC BBSPLLN0 BUSPTRC_B2 BUSPTRC BUSPTRC BUSPTRC_B3 BUSPTRC BUSPTRC BUSPTRC_B4 BUSPTRC BUSPTRC BUSPTRC_B5 BUSPTRC BUSPTRC BUSPTRC_B6 BUSPTRC BUSPTRC BUSPTRC_B7 BUSPTRC BUSPTRC Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 26 BZNPDIF BZNPDIF_Z2 BZNPDIF BZNPDIF BZNPDIF_Z3 BZNPDIF BZNPDIF BZNPDIF_Z4 BZNPDIF BZNPDIF BZNPDIF_Z5 BZNPDIF BZNPDIF BZNPDIF_Z6 BZNPDIF BZNPDIF BZNSPDIF_A BZNSPDIF BZASGAPC BZASPDIF BZNSGAPC BZNSPDIF BZNSPDIF_B BZNSPDIF BZBSGAPC BZBSPDIF BZNSGAPC BZNSPDIF Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 27 DRPRDRE DRPRDRE ECPSCH ECPSCH ECPSCH ECRWPSCH ECRWPSCH ECRWPSCH EF2PTOC EF2LLN0 EF2PTRC EF2PTRC EF2RDIR EF2RDIR GEN2PHAR GEN2PHAR PH1PTOC PH1PTOC EF4PTOC EF4LLN0 EF4PTRC EF4PTRC EF4RDIR EF4RDIR GEN4PHAR GEN4PHAR PH1PTOC PH1PTOC Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 28 L6CPTRC LAPPGAPC LAPPLLN0 LAPPPDUP LAPPPDUP LAPPPUPF LAPPPUPF LCCRPTRC LCCRPTRC LCCRPTRC LCNSPTOC LCNSPTOC LCNSPTOC LCNSPTOV LCNSPTOV LCNSPTOV LCP3PTOC LCP3PTOC LCP3PTOC LCP3PTUC LCP3PTUC LCP3PTUC LCPTTR LCPTTR LCPTTR LCZSPTOC LCZSPTOC LCZSPTOC Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 29 OEXPVPH OOSPPAM OOSPPAM OOSPPAM OOSPTRC OV2PTOV GEN2LLN0 OV2PTOV OV2PTOV PH1PTRC PH1PTRC PAPGAPC PAPGAPC PAPGAPC PCFCNT PCGGIO PCFCNT PH4SPTOC GEN4PHAR GEN4PHAR OCNDLLN0 PH1BPTOC PH1BPTOC PH1PTRC PH1PTRC PHPIOC PHPIOC PHPIOC Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 30 SPGAPC SPGGIO SPGAPC SSCBR SSCBR SSCBR SSIMG SSIMG SSIMG SSIML SSIML SSIML STBPTOC STBPTOC BBPMSS STBPTOC STEFPHIZ STEFPHIZ STEFPHIZ STTIPHIZ STTIPHIZ STTIPHIZ SXCBR SXCBR SXCBR SXSWI SXSWI SXSWI Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 31 WRNCALH WRNCALH ZC1PPSCH ZPCPSCH ZPCPSCH ZC1WPSCH ZPCWPSCH ZPCWPSCH ZCLCPSCH ZCLCPLAL ZCLCPSCH ZCPSCH ZCPSCH ZCPSCH ZCRWPSCH ZCRWPSCH ZCRWPSCH ZCVPSOF ZCVPSOF ZCVPSOF ZGVPDIS ZGVLLN0 PH1PTRC PH1PTRC ZGVPDIS ZGVPDIS ZGVPTUV ZGVPTUV Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 32 ZMFPDIS ZMFPDIS ZMFPTRC ZMFPTRC ZMMMXU ZMMMXU ZMHPDIS ZMHPDIS ZMHPDIS ZMMAPDIS ZMMAPDIS ZMMAPDIS ZMMPDIS ZMMPDIS ZMMPDIS ZMQAPDIS ZMQAPDIS ZMQAPDIS ZMQPDIS ZMQPDIS ZMQPDIS ZMRAPDIS ZMRAPDIS ZMRAPDIS ZMRPDIS ZMRPDIS ZMRPDIS ZMRPSB ZMRPSB ZMRPSB ZSMGAPC ZSMGAPC ZSMGAPC Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 33: Section 2 Safety Information

    Working in a high voltage environment requires serious approach to avoid human injuries and damage to equipment. M2362-2 v1 Do not touch circuitry during operation. Potentially lethal voltages and currents are present. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 34 Take adequate measures to protect the eyes. Never look into the laser beam. GUID-11CCF92B-E9E7-409C-84D0-DFDEA1DCBE85 v2 The IED with accessories should be mounted in a cubicle in a restricted access area within a power station, substation or industrial or retail environment. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 35: Caution Signs

    Be careful and check regulations before making the change. Note signs IP1497-1 v1 M19-2 v3 Observe the maximum allowed continuous current for the different current transformer inputs of the IED. See technical data. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 37: Section 3 Available Functions

    Additional security logic for differential protection Impedance protection ZMQPDIS, Distance protection zone, ZMQAPDIS quadrilateral characteristic ZDRDIR Directional impedance quadrilateral ZMCPDIS, Distance measuring zone, ZMCAPDIS quadrilateral characteristic for series compensated lines Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 38 Power swing logic 1-B15 1-B15 PSPPPAM Poleslip/out-of-step protection OOSPPAM Out-of-step protection ZCVPSOF Automatic switch onto fault logic, 1-B15 1-B15 voltage and current based ZGVPDIS Underimpedance protection for 0–2 1-B14 1-B14 generators and transformers Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 39: Back-Up Protection Functions

    1-C35 1-C35 1-C35 BRCPTOC Broken conductor check CBPGAPC Capacitor bank protection NS2PTOC 46I2 Negative sequence time overcurrent protection for machines VRPVOC Voltage restrained overcurrent 1-C35 1-C35 1-C35 protection Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 40 6-E01 6-E01 SAPFRC Rate-of-change of frequency 6-E01 6-E01 6-E01 protection Multipurpose protection CVGAPC General current and voltage 6-F02 6-F02 protection General calculation SMAIHPAC Multipurpose filter 1) 67 requires voltage 2) 67N requires voltage Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 41: Control And Monitoring Functions

    DPGAPC Generic communication function for Double Point indication SPC8GAPC Single point generic control function 8 signals AUTOBITS Automation bits, command function for DNP3.0 SINGLECMD Single command, 16 signals Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 42 AND, GATE, INV, Extension logic package (see LLD, OR, Table 7) PULSETIMER, RSMEMORY, SLGAPC, SRMEMORY, TIMERSET, VSGAPC, XOR FXDSIGN Fixed signal function block B16I Boolean to integer conversion, 16 bit Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 43 Comparator for integer inputs REALCOMP Comparator for real inputs Table 3: Total number of instances for basic configurable logic blocks Basic configurable logic block Total number of instances GATE PULSETIMER RSMEMORY SRMEMORY TIMERSET Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 44 Switch controller SXSWI Circuit switch QCRSV Apparatus control RESIN1 RESIN2 POS_EVAL Evaluation of position indication XLNPROXY Proxy for signals from switching device via GOOSE GOOSEXLNRCV GOOSE function block to receive a switching device Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 45 Table 6: Total number of instances for configurable logic blocks Q/T Configurable logic blocks Q/T Total number of instances ANDQT INDCOMBSPQT INDEXTSPQT INVALIDQT INVERTERQT ORQT PULSETIMERQT RSMEMORYQT SRMEMORYQT TIMERSETQT XORQT Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 46 Disturbance report A4RADR, SPGAPC Generic communication function for Single Point indication SP16GAPC Generic communication function for Single Point indication 16 inputs MVGAPC Generic communication function for measured values Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 47 Supervison status for IEC 60870-5-103 I103USRDEF Status for user defined signals for IEC 60870-5-103 L4UFCNT Event counter with limit supervision TEILGAPC Running hour meter Metering PCFCNT Pulse-counter logic ETPMMTR Function for energy calculation and demand handling Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 48: Communication

    GOOSE function block to receive a measurand value GOOSESPRCV GOOSE function block to receive a single point value VCTRSEND Horizontal communication via GOOSE for VCTR GOOSEVCTRRCV Horizontal communication via GOOSE for VCTR Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 49 Precision time protocol FRONTSTATUS Access point diagnostic for front Ethernet port SCHLCCH Access point diagnostic for non- redundant Ethernet port RCHLCCH Access point diagnostic for redundant Ethernet ports Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 50 ZCLCPSCH Local acceleration logic 1-B15 1-B15 1-K01 1-K01 ECPSCH Scheme communication logic for residual overcurrent protection ECRWPSCH Current reversal and weak-end infeed logic for residual overcurrent protection Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 51: Basic Ied Functions

    Signal matrix for binary inputs SMBO Signal matrix for binary outputs SMMI Signal matrix for mA inputs SMAI1 - SMAI12 Signal matrix for analog inputs 3PHSUM Summation block 3 phase Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 52 Parameter setting function for HMI in PCM600 FNKEYMD1– FNKEYMD5 LEDGEN General LED indication part for LHMI OPENCLOSE_LED LHMI LEDs for open and close keys GRP1_LED1– Basic part for CP HW LED indication module GRP1_LED15 GRP2_LED1– GRP2_LED15 GRP3_LED1– GRP3_LED15 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 53: Section 4 Starting Up

    Before starting up commissioning at site, check that the following items are available. • Single line diagram • Protection block diagram • Circuit diagram • Setting list and configuration • RJ-45 Ethernet cable (CAT 5) Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 54: Checking The Power Supply

    Check also the self-supervision function in Main menu/Diagnostics/IED status/ General menu in local HMI to verify that the IED operates properly. Set the IED time if no time synchronization source is configured. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 55: Ied Start-Up Sequence

    Each IED has an RJ-45 Ethernet interface connector on the front. The front Ethernet connector is recommended to be used for communication with PCM600. When an Ethernet-based station protocol is used, PCM600 communication can use the same Ethernet port and IP address. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 56 An ethernet cable (max 2 m length) with RJ-45 connectors is needed to connect two physical Ethernet interfaces together without a hub, router, bridge or switch in between. Select Search programs and files in the Start menu in Windows. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 57 Section 4 1MRK 504 165-UEN A Starting up IEC13000057-1-en.vsd IEC13000057 V1 EN-US Figure 3: Select: Search programs and files Type View network connections and click on the View network connections icon. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 58 Right-click and select Properties. IEC13000059-1-en.vsd IEC13000059 V1 EN-US Figure 5: Right-click Local Area Connection and select Properties Select the TCP/IPv4 protocol from the list of configured components using this connection and click Properties. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 59 IP address is not set to be obtained automatically by the IED, see Figure 7. The IP address must be different from the IP address chosen for the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 60: Writing An Application Configuration To The Ied

    When the IED is set in configuration mode, all functions are blocked. The red LED on the IED flashes, and the green LED is lit while the IED is in the configuration mode. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 61: Checking Ct Circuits

    While the CT primary is energized, the secondary circuit shall never be open circuited because extremely dangerous high voltages may arise. Both the primary and the secondary sides must be disconnected from the line and the IED when plotting the excitation characteristics. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 62: Checking Vt Circuits

    In this position, the current and voltage enter the protection, but the alarm and trip circuits are still isolated and the IED is in test mode. Before removing the test handle, check the measured values in the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 63: Checking The Binary Input/Output Circuits

    4.10.2 Binary output circuits M11722-8 v3 Preferably, disconnect the binary output connector from the binary output cards. Check all connected signals so that both load and polarity are in accordance with IED specifications. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 64: Checking Optical Connections

    An IED equipped with optical connections has an minimum space requirement of 180 mm for plastic fiber cables and 275 mm for glass fiber cables. Check the allowed minimum bending radius from the optical cable manufacturer. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 65: Section 5 Configuring The Ied And Changing Settings

    IED. After that time has elapsed, it will be safe to turn the IED off, no data will be lost. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 66: Configuring Analog Ct Inputs

    Take the rated permissive overload values for the current inputs into consideration. Supervision of input/output modules M11728-2 v3 I/O modules configured with PCM600 (BIM, BOM or IOM) are supervised. I/O modules that are not configured are not supervised. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 67 Each logical I/O module has an error flag that indicates signal or module failure. The error flag is also set when the physical I/O module of the correct type is not detected in the connected slot. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 69: Section 6 Establishing Connection And Verifying The Spa/Iec Communication

    • plastic fibres with connector type HFBR • glass fibres with connector type ST When using the IEC protocol, the rear SPA/IEC port must be set for IEC use. Procedure: Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 70: Verifying The Communication

    IEC. The configuration must be made with the PCM600 software. Verify that the event is presented in the IEC master system. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 71: Fibre Optic Loop

    Losses in connection box, two contacts (0.5 dB/contact) 1 dB Losses in connection box, two contacts (1 dB/contact) 2 dB Margin for 2 repair splices (0.5 dB/splice) 1 dB Maximum total attenuation 11 dB 7 dB Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 73: Section 7 Establishing Connection And Verifying The Lon Communication

    IEDs through the LON bus from the operator’s workplace, from the control center and also from other IEDs via bay-to-bay horizontal communication. For LON communication an SLM card should be ordered for the IEDs. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 74: The Lon Protocol

    Use the LON Network Tool (LNT) to set the LON communication. This is a software tool applied as one node on the LON bus. To communicate via LON, the IEDs need to know Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 75 Location 0 - 6 No value Location of the node *Can be viewed on the local HMI ADE settings are available on the local HMI under Main menu/Configuration/ Communication/Station communicaton/LON/ADE:1 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 76: Optical Budget Calculation For Serial Communication With Lon

    Losses in connection box, two contacts (0.75 dB/contact) 1.5 dB Losses in connection box, two contacts (1dB/contact) 2 dB Margin for repair splices (0.5 dB/splice) 0.5 dB Maximum total attenuation 11 dB 7 dB Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 77: Section 8 Establishing Connection And Verifying The Iec 61850 Communication

    There are no settings needed for the IEC/UCA 61850-9-2LE communication in the local HMI branch Station communication. Make sure that the optical fibres are connected correctly. Communication is enabled whenever the merging unit starts sending data. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 78: Verifying The Communication

    Ethernet ports. Verify that either signal status (depending on which connection that was removed) is shown as Error and the that other signal is shown as Ok. Be sure to re-connect the removed connection after completed verification. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 79: Section 9 Establishing Connection And Verifying The Ieee C37.118/1344 Communication

    1.1. Make sure that the operation of at least one PMU instance (e.g. PMU1) is On. 1.2. Enable sending the frequency data by setting the parameter SendFreqInfo to On. Check the operation of the required phasor channels (PHASORREPORT) by navigating to: Main menu/Configuration/Communication/Station communication/phasor measurement/PMU Report/PHASORREPORT:x. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 80: Setting The Pmu Station Communication (Pmu Configuration)

    LAN IP address of the PC is used, where the PDC client tool is installed. 3.3. The default parameter settings can be used for the rest of parameters for the first UDP group. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 81: Setting The Tcp/Udp Client Communication

    IEEE C37.118 connection with the PMU: Set the IP stack on PMU Connection Tester to IPv4. Note that the default IP stack on PMU Connection Tester tool is IPv6. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 82 2.1. Set Host IP to the PMU IP address configured for the port in use. Here the LANAB:1 IPAddress (192.168.1.10) is set. 2.2. Set Port to the IED's TCP port set in the PMU under parameter C37.118TCPport (4712 is default). Alternatively, in order to make an Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 83 3.2. Click the Configure Alternate Command Channel to configure the TCP channel. A new window will pop up. A TCP channel needs to be configured in order to control the UDP data communicatiuon and transfer the header, configuration and command frames. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 84: Verifying The Communication

    Alternatively, the PMU Connection Tester tool can be used to verify the IEEE C37.118/1344 communication. The section Setting the TCP/UDP client communication explains how to set the PMU Connection Tester parameters in order to establish an IEEE C37.118 connection with the PMU. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 85: Verifying The Ieee C37.118/1344 Tcp Communication

    Now it should be possible to see the streaming synchrophasor data. In the Graph tab, observe the Frequency, data Reporting Rate, Phasor names, and Phase angles of the reported synchrophasors. Observe the real-time frame details of the Data Frame in the bottom of the window. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 86 Open the drop-down menu in the Command field. There is a list of commands that can be sent from the client (PMU Connection Tester) to the PMU. Try different commands and make sure that the PMU is receiving and responding to them. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 87 If the HeaderFrame is not included, ask the PMU to send the header frame via the Send Header Frame command (Previous stage). Open each message type and observe the content of each message. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 88 It is also possible to capture the IEEE C37.118 synchrophasor data in an Excel file. This is done by navigating to File/Capture/Start Stream Debug Capture... The tool will ask to Set Stream Debug Capture File Name and path to save the capture file. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 89 IEC140000142 V1 EN-US Figure 14: Start capturing the IEEE C37.118 synchrophasor data • The synchrophasor data capturing process can be stopped at any point of time by navigating to File/Capture/Stop Stream Debug Capture... Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 90 Phasor names on top of each column (See figure 16), the capture process should start before connecting the PMU Connection Tester to the PMU, i.e. first start the capturing and then click Connect. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 91: Verifying The Ieee C37.118/1344 Udp Communication

    Verifying the UDP communication using PMU Connection Tester • Now it should be possible to see the streaming synchrophasor data. • Verify the communication by following the same steps as in section Verifying the IEEE C37.118/1344 TCP communication. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 92: Optical Budget Calculation For Pmu - Pdc Communication

    62.5/125 µm curve represents the remaining optical budget at any link length, which is available for overcoming non-fiber cable related losses. Losses in the connectors and splices are typically 0.3dB/connection. The user must reserve 3dB spare for the uncertainty of the measurements. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 93: Section 10 Testing Ied Operation

    The voltages and currents from the test equipment must be obtained from the same source and they must have minimal harmonic content. If the test equipment cannot indicate the phase angle, a separate phase-angle measuring instrument is necessary. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 94 Some time must pass before the IED is restarted. For more information about the flash memory, refer to section “Configuring the IED and changing settings”. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 95: Preparing The Ied To Verify Settings

    In certain cases, only modes with a high probability of coming into operation need to be checked when commissioned to verify the configuration and settings. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 96: Activating The Test Mode

    Use COMBITEST test system to prevent unwanted tripping when the handle is withdrawn, since latches on the handle secure it in the half withdrawn position. In this position, all voltages and currents are restored and any re-energizing transients Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 97: Connecting The Test Equipment To The Ied

    IED under test. To ensure correct results, make sure that the IED as well as the test equipment are properly earthed before testing. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 98: Releasing The Function To Be Tested

    Any function is blocked if the corresponding setting in the local HMI under Main menu/Test/Function test modes menu remains On, that is, the parameter Blocked is set to Yes and the parameter TESTMODE under Main menu/Test/IED test mode remains Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 99: Verifying Analog Primary And Secondary Measurement

    Inject an unsymmetrical three-phase voltage and current, to verify that phases are correctly connected. If some setting deviates, check the analog input settings under Main menu/Configuration/Analog modules Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 100: Testing The Protection Functionality

    Use the disturbance handling tool in PCM600 to evaluate that the protection function has received the correct data and responded correctly (signaling and timing). • Use the event viewer tool in PCM600 to check that only expected events have occurred. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 101: Forcing Of Binary Input/Output Signals For Testing

    Test/IED test mode/TESTMODE:1. IEC15000029 V1 EN-US Exit back to the root menu. Select Yes in the save dialogue box. Once the IED is in test mode the yellow Start LED starts to blink. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 102: Enable Forcing Using Testmode Function Block

    Use the up/down arrows on the LHMI to change the signal value or the appropriate menu in PCM600. The status of the signal changes automatically to Forced (i.e. there is no need to set the status to Forced manually). Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 103 Freezing a signal value without changing it GUID-FD76AAC1-7098-47D3-A3A1-6ACDF509ED91 v1 • Set the status of a signal to Forced, in the forcing menu that corresponds to the I/O card in question. See example of LHMI menu in figure Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 104: Forcing By Using Pcm600

    Click Forcing Session in the menu IED/Start Forcing. IEC15000023 V1 EN-US Click Start editing signal value for forcing on the tool bar. IEC15000024 V1 EN-US The Signal Monitoring menu changes and indicates the forcing values that can be edited. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 105: How To Undo Forcing Changes And Return The Ied To Normal Operation

    How to undo forcing changes and return the IED to normal operation GUID-00E2BAD8-A29E-4B9D-80E6-E12F59E019BD v1 Regardless of which input/output signals have been forced, all forced signals will return to their normal states immediately when the IED is taken out of test mode. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 106: Undo Forcing By Using Testmode Component

    PCM600 will revert all forced signals back to unforced and the real signal values will immediately take effect again. This may change both binary input values and output relay states and will undo any forcing done by using the LHMI. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 107 Section 10 1MRK 504 165-UEN A Testing IED operation If the IED is left in test mode, then it is still possible to perform new forcing operations, both from LHMI and from PCM600 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 109: Section 11 Testing Functionality By Secondary Injection

    The Manual Trig can be started in two ways: From the local HMI under Main menu/Disturbance records. 1.1. Enter on the row at the bottom of the HMI called Manual trig. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 110: Event Recorder (Er) And Event List (El)

    PCM600 as follows: on the local HMI under Main menu/Events, or in more details via the Event Viewer in PCM600. The internal FIFO register of all events will appear when the event viewer is launched. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 111: Identifying The Function To Test In The Technical Reference Manual

    Depending on the power transformer vector group (Yd and so on), the single- phase injection current may appear as differential current in one or two phases and the operating value of the injected single-phase current will be different. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 112: Completing The Test

    Note as well that used CT input in the IED must have ratio set as 1:1. This is essential for the measurement of the expected Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 113: Completing The Test

    11.3.3 Restricted earth fault protection, low impedance REFPDIF SEMOD55252-82 v8 Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.3.3.1 Verifying the settings SEMOD55252-86 v11 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 114: Completing The Test

    Verifying the settings GUID-D9F626D4-4038-416F-888E-D3DB5047E79A v1 Prepare the IED for verification of settings outlined in section 1 “Overview” and section 2 “Preparing for test” in this chapter. Current variation local criteria GUID-804E13B6-DC31-487B-A582-7886B1EF3EB7 v2 Procedure Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 115 Decrease the current slowly and note the reset value. Connect a trip output contact to a timer. Set the injected current to 200 % of the operate level of the tested stage, switch on the current and check the time delay. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 116: Completing The Test

    21. In cases where the load encroachment characteristic is activated tests according to the adjusted figures should be carried out. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 117 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. X1Zx 120° R (Ohm/phase) 20° 40% of RLdFw 80% of RLdFw 0.5 x RFPPZx IEC05000368-4-en.vsdx IEC05000368 V4 EN-US Figure 23: Distance protection characteristic with test points for phase-to- phase measurements Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 118 Exact –0.5 x R1 tan(ArgNegRes=30°) –0.37 x X1 0.5 x X1 0.5 x R1 Only used when RLdFw > 0.5 x RFPP 0.5 x RFPP Table is used in conjunction with figure 23. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 119 ArgLd = angle for the maximal load transfer 0.85 x RFPE RLdFwset x tan(ArgLdSet) RLdFw RLdFw –0.1072 x RLdFw Exact: 0.4 x RFPE x tan (ArgDir=20°) 0.4 x RLdFw Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 120: Measuring The Operating Limit Of Set Values

    (directional angles). Directional functionality testing (trip inside, no-trip outside) should always be made for all impedance zones set with directionality (forward or reverse). 11.4.1.2 Measuring the operating time of distance protection zones M14944-154 v6 Procedure: Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 121: Completing The Test

    To verify the settings the operating points according to figures should be tested. See also tables for information. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 122 When RLdFwPE > RFFwPE 0.85·[X1+XN] R≈0.491·(X1+XN)+RFFwPE 0.85·[X1+XN]·1/tan(60°)+RFFwPE 0.85·[X1+XN] Can be limited by RFFwPE -0.85·[X1+XN]· tan (AngNegRes-90°) RFFwPE·tan (ArgLd) Only when RLdFw < RFFwPE RFFwPE -0.5·RLdFw·tan (ArgDir) 0.5·RLdFw Table is used together with figure 25. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 123 When RLdFw > 0,5·RFFwPP 0.85·X1 R=0.491·X1+0.5 RFFwPP 0.85·X1·1/tan(60°)+0.5 RFFwPP 0.85·X1 Can be limited by RFFwPP -0.85·X1·tan (AngNegRes-90°) 0.5·RFFwPP·tan (ArgLd) Only when RLdFW < RFFwPP 0.5·RFFwPP -0.5·RLdFw·tan (ArgDir) 0.5·RLdFw Table is used together with figure 26. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 124: Measuring The Operating Limit Of Set Values

    Ensure that the maximum continuous current in an IED does not exceed four times its rated value, if the measurement of the operating characteristics runs under constant voltage conditions. To verify the mho characteristic, at least two points should be tested. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 125: Phase-To-Phase Faults

    After the timer tPP for the actual zone has elapsed, also the signals TRIP, TRPP and TRx shall be activated. 11.4.3.2 Phase-to-earth faults M14944-393 v7 For simplicity, the same test points as for phase-to-phase faults are proposed, but considering new impedance values. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 126: Faulty Phase Identification With Load Encroachment Fmpspdis

    (mho) functions. 11.4.5 Distance protection zones, quadrilateral characteristic, separate settings ZMRPDIS GUID-A35C2DED-70A6-4E96-864D-3A6C1147B350 v3 Prepare the IED for verification of settings as outlined in section "Preparing for test" in this chapter. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 127 13 are valid for this case. When the load current compensation is inactive, the dotted lines and test point 13 are valid. Test points 5, 6, and 7 are not valid for this measurement. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 128 80% of RLdFw alt. 80% of RFPEZx RFPEZx (Load encroachment) IEC05000369-4-en.vsdx IEC05000369 V4 EN-US Figure 30: Distance protection characteristic with test points for phase-to- earth measurements Table is used in conjunction with figure 30. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 129 (2 x X1 (2 x X1 + X0 2 x R1 + R0 0.8 x (2 x X1 + X0 0.8 x (2 x R1 + R0 +RFPE Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 130: Measuring The Operating Limit Of Set Values

    27. Test points 8, 9, 10 and 11 are intended to test the directional lines of impedance protection. Since directionality is a common function for all 5 measuring zones, it is only Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 131: Measuring The Operating Time Of Distance Protection Zones

    To verify the settings the operating points according to figures should be tested. See also tables for information. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 132 Operating characteristic for phase selection function, forward direction single-phase faults phase ArgLd ArgNegRes 60° phase ArgDir 50% RLdFw 0.5·RFFwPP IEC09000735-3-en.vsd IEC09000735 V3 EN-US Figure 32: Operating characteristic for phase selection function, forward direction phase-to-phase faults Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 133: Measuring The Operating Limit Of Set Values

    0.85·X1 -0.85·X1·tan (AngNegRes-90°) 0.5·RFFwPP·tan (ArgLd) 0.5·RFFwPP -0.5·RLdFw·tan (ArgDir) 0.5·RLdFw The table showing test points for phase-to-phase loops is used together with figure 11.4.6.1 Measuring the operating limit of set values GUID-B1B7DEB6-7BC3-4A90-8D8F-E4E69B434AFA v3 Procedure: Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 134: Completing The Test

    31. In cases where the load encroachment characteristic is activated tests according to the adjusted figures should be carried out. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 135 IEC05000368 V4 EN-US Figure 33: Distance protection characteristic with test points for phase-to- phase measurements Table 30: Test points for phase-to-phase loops L1-L2 (Ohm/Loop) Test point Reach Set value Comments Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 136 Exact –0.5 x R1 tan(ArgNegRes=30°) –0.23 x X1 0.8 x X1 Exact –0.5 x R1 tan(ArgNegRes=30°) –0.37 x X1 0.5 x X1 0.5 x R1 0.5 x RFPPZx Table is used in conjunction with figure 33. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 137 ArgLd = angle for the maximal load transfer 0.85 x RFPEZx RLdFwset x tan(ArgLdSet) RLdFw RLdFw –02143 x RLdFw Exact: 0.8 x RFPEZx x tan (ArgDir=20°) 0.8 x RLdFw Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 138: Measuring The Operating Limit Of Set Values

    Directional functionality testing (trip inside, no-trip outside) should always be made for all impedance zones set with directionality (forward or reverse). 11.4.7.2 Measuring the operating time of distance protection zones GUID-BB93C603-F43E-40CB-8EFA-3B0F280C011D v5 Procedure: Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 139: Completing The Test

    To verify the settings for the operating points according to the following fault types should be tested: • One phase-to-phase fault • One phase-to-earth fault The shape of the operating characteristic depends on the values of the setting parameters. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 140 0.8 x R1 + RFPPZx/2 0.5 x X1 0.5 x R1 + RFPPZx/2 ArgLd = angle for the maximal load 0.85 x RFPPZx x tan (ArgLd) transfer 0.85 x RFPPZx Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 141 80% of RLdFw alt. 80% of RFPEZx RFPEZx (Load encroachment) IEC05000369-4-en.vsdx IEC05000369 V4 EN-US Figure 36: Distance protection characteristic with test points for phase-to- earth measurements Table is used in conjunction with figure 36. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 142: Measuring The Operating Limit Of Set Values

    Subject the IED to healthy normal load conditions for at least two seconds. Apply the fault condition and slowly decrease the measured impedance to find the operating value of the phase-to-phase fault for zone 1 according to Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 143: Completing The Test

    Power swing detection ZMRPSB M13888-2 v9 The aim is to verify that the settings of the Power swing detection function ZMRPSB is according to the setting table and to verify that ZMRPSB operates as expected. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 144 ZMRPSB. The proposed test points for validation of the settings are numbered according to figure Test of the interactions or combinations that are not configured are not considered in this instruction. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 145: Verifying The Settings

    X1OutFw = X1OutRv = X1InRv + (RLdOutFw - RLdInFw) 11.4.9.1 Verifying the settings M13888-11 v6 Preconditions The following output signal shall be configured to binary output available: ZOUT, measured impedance within outer impedance boundary. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 146: Testing The Power Swing Detection Function Zmrpsb

    ZMRPSB is activated. Make a test sequence so that a single-phase to earth fault occurs after that the trajectory of the impedance has passed the outer and inner boundary of Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 147: Testing The Block Input, Interaction Between Fdpspdis Or Frpspdis And Zmrpsb

    STPSD input signal to some other functional signal, which is used for testing purposes. Make sure that the existing configuration permits monitoring of the CS, TRIP signals on the binary outputs of the IED. If not, configure connections to unused binary outputs, for test purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 148: Testing The Carrier Send And Trip Signals

    BLKZMUR must appear together with the fault and must remain active until the fault has been switched off plus the time delay, as set on the tBlkTr timer. Initiate a phase-to-phase fault within the operating area of both power-swing zones. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 149: Checking The Underreaching Zone

    M14946-70 v2 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 150: Pole Slip Protection Pspppam

    With reduced amplitude of the injected voltage to 0.8 UBase the current amplitude and angle is changed via ZC + (ZA – ZC)/2 to a value corresponding to half IBase and 180° between the injected current and voltage. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 151 Now the signals TRIP2 and TRIP should be activated. Zone 1 Zone 2 X’ Pole slip impedance movement Zone 2 TripAngle Zone 1 WarnAngle IEC07000099_2_en.vsd IEC07000099 V2 EN-US Figure 38: Setting of the pole slip protection PSPPPAM Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 152: Completing The Test

    A parameter setting is available to take into account the circuit breaker opening time. If there are several out-of-step relays in the power system, then the one which finds the center of oscillation in its zone 1 should operate first. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 153: Verifying The Settings

    The rating of the analogue channels is considered in order to avoid any hardware damage. The test current is lower than the continuous permissive overload current I of the protection current channels of ovrl the transformer module. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 154 If the test voltage is lower than V (or in opposition), then the test is related to t,RZ1 the zone 1; if the test voltage is higher than V , then the test is related to the t,RZ1 zone 2. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 155 TRM module is 420 V; so the previous voltages may be applied to the analog channels of the IED continuously. Limitations may be related to the available test set; the current I Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 156 The present procedure avoids tests of points of the line SE-RE that are too close to the R-axis because in that case the voltage is close to zero and, therefore, the impedance may approach a not defined quantity 0/0. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 157: Test Of Point Re (R Fwdr , X Fwdx )

    Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 1 1 11931 95 1 × × × × t FwdZ 13 8 VT p (Equation 17) EQUATION14057 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 158 EQUATION14057 V1 EN-US ForwardX 59 33     arctan arctan 82. . 14° ∠  =  =   ForwardR 8 19     (Equation 22) EQUATION14058 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 159 Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 0 9 11931 77 81 × × × × t FwdZ 13 8 VT p (Equation 27) EQUATION14063 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 160 EQUATION14063 V1 EN-US ForwardX 59 33     arctan arctan 82. . 14° ∠  =  =   ForwardR 8 19     (Equation 32) EQUATION14058 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 161: Test Of The Boundary Between Zone 1 And Zone 2, Which Is Defined By The Parameter Reachz1

    Go to Main menu/Test/Function status/Impedance protection/ OutOfStep(78,Ucos)/OOSPPAM(78,Ucos):1/Outputs to check the available service values of the function block OOSPPAM. • Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 162 Define the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 1 1 1435 11 44 × × × × t RZ 13 8 VT p (Equation 41) EQUATION14065 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 163 Go to Main menu/Test/Function status/Impedance protection/ OutOfStep(78,Ucos)/OOSPPAM(78,Ucos):1/Outputs to check the available service values of the function block OOSPPAM. • Apply the following three-phase symmetrical quantities (the phase angle is related to phase L1): Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 164 Define the following three-phase symmetrical quantities (the phase angle is related to phase L1): VT s 0 9 1435 9 36 × × × × t RZ 13 8 VT p (Equation 51) EQUATION14066 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 165 × 9000 (Equation 56) EQUATION14062 V1 EN-US ∠I = 180º frequency of I = 49.5 Hz Expected result: start of the protection function and trip in zone 1 when trip conditions are fulfilled. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 166: Test Of The Point Se (R Rvsr , X Rvsx )

    ROTORANG = -3.06 rad Note that these values identify a point inside the lens characteristic in zone 1 that is close to the point SE. The START is issued, but no TRIP is performed. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 167 (Equation 65) EQUATION14059 V1 EN-US ∠I = 0º frequency of I = 50 Hz 10459 1 162 × × 9000 (Equation 66) EQUATION14062 V1 EN-US ∠I = 180º frequency of I = 50.5 Hz Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 168 R= –0.32% • X=–32.57% • ROTORANG= 0.08 rad Note that these values identify a point outside the lens characteristic, even if it is close to the point SE. Neither START nor TRIP is issued. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 169 (Equation 75) EQUATION14059 V1 EN-US ∠I = 0º frequency of I = 50 Hz 10459 1 162 × × 9000 (Equation 76) EQUATION14062 V1 EN-US ∠I = 180º frequency of I = 50.5 Hz Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 170: Automatic Switch Onto Fault Logic Zcvpsof

    A three-phase fault with zero impedance and a three-phase fault with an impedance corresponding to the whole line is applied. This fault shall cause an instantaneous trip and result in a TRIP indication. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 171: Activating Zcvpsof Externally

    M13850-41 v5 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 172: Phase Preference Logic Pplphiz

    Trip No Trip 231a No Trip Trip Trip No Trip No Trip Trip 312a Trip No Trip No Trip Trip No Trip Trip 321a No Trip Trip No Trip Trip No Trip Trip Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 173: Completing The Test

    Trip No Trip 231a No Trip Trip Trip No Trip No Trip Trip 312a Trip No Trip No Trip Trip No Trip Trip 321a No Trip Trip No Trip Trip No Trip Trip Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 174: Completing The Test

    If the measurement of the operating characteristics runs under constant voltage conditions, ensure that the maximum continuous current in an IED does not exceed four times its rated value. To verify the zone 1 mho characteristic, at least two points must be tested. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 175 After the operate time delay for the zone 1 has elapsed, the signals TRIP and TRZ1 shall be activated. To verify zone 2 and zone 3 mho characteristic, at least two points must be tested. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 176 TRIP and TRZx (where x is 2 or 3 depending on selected zone) shall be activated. Load encroachment GUID-4E0958A9-000E-440F-A880-89B54774AC63 v3 Load encroachment operates on the same measuring principles as the impedance measuring zones. Thus, it is necessary to follow the same principles as for distance Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 177: Completing The Test

    Tests/Function test modes/Impedance/ZGVPDIS/1: ZGVPDIS for the function, or for each individual function in a chain, to be tested next. Remember to set the parameter Blocked to Yes, for each individual function that has been tested. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 178: Current Protection

    M11754-24 v5 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 179: Directional Phase Overcurrent Protection, Four Steps Oc4Ptoc

    If 2 out of 3 currents are chosen for operation: The phase angle of the phase-to-phase voltage L1L2 is the reference for L1Phase. If 3 out of 3 currents are chosen for operation: The voltage angle of phase L1 is the reference. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 180: Completing The Test

    InstResidualOverCurrent(50N,IN>>)/EFPIOC(50N;IN>>):x, where x = 1, 2, and 3. The Signal Monitoring in PCM600 shows the same signals that are available on the local HMI. To verify the settings the following fault type should be tested: • Phase-to-earth fault Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 181: Measuring The Operate Limit Of Set Values

    The Signal Monitoring in PCM600 shows the same signals that are available on the local HMI. 11.5.4.1 Four step directional earth fault protection SEMOD53296-208 v7 Connect the test set for single current injection to the appropriate IED terminals. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 182: Four Step Non-Directional Earth Fault Protection

    Off. Restore connections and settings to their original values, if they were changed for testing purposes. 11.5.5 Four step negative sequence overcurrent protection NS4PTOC GUID-EB1A8DFD-5BAC-4024-ADA2-D9BE7A2B50A0 v2 Prepare the IED for verification of settings as outlined in section "Preparing for test" in this chapter. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 183: Completing The Test

    SEMOD53296-122 v4 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 184: Sensitive Directional Residual Overcurrent And Power Protection Sdepsde

    Take setting RCAComp into consideration if not equal to 0. Inject current until the function picks up, and make sure that the operate current of the set directional element is equal to the INcosPhi> setting. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 185 PCM600 when the IED is in online mode. Compare the voltage with the set value UNRel> . Continue to test another function or complete the test by setting the test mode to Off. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 186 Section 11 1MRK 504 165-UEN A Testing functionality by secondary injection RCADir Operate area 3 × ROADir IEC06000650_2_en.vsd IEC06000650 V2 EN-US Figure 45: Characteristic with ROADir restriction Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 187 Compare the result with the set value and make sure that the new injected 3I · 3U · cos φ is equal to the setting SN>. Take the set characteristic into consideration, see figure and figure 46. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 188 Compare the result with the expected value. The expected value depends on whether definite or inverse time was selected. Continue to test another function or complete the test by setting the test mode to Off. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 189 Inject a voltage 0.8 · UNRel> and a current high enough to operate the directional function at the chosen angle. Increase the voltage until the directional function is released. Compare the measured value with the set UNRel> operate value. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 190: Completing The Test

    With setting Itr = 101%IBase1 and injection current 1.50 · IBase1, the trip time from zero content in the memory shall be 0.60 · Time Constant 1 (Tau1). 12. Check that all trip and alarm contacts operate according to the configuration logic. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 191: Completing The Test

    Apply the fault condition, including START of CCRBRF, with a current below the set IP>. Repeat the fault condition and increase the current in steps until a trip occurs. Compare the result with the set IP>. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 192: Checking The Residual (Earth Fault) Current Operate Value In> Set Below Ip

    Apply the fault condition, including start of CCRBRF, well above the set current value. Verify that no re-trip, but back-up trip is achieved after set time. RetripMode = CB Pos Check Checking the re-trip with current check, M12104-48 v7 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 193: Verifying The Back-Up Trip Mode

    IP> but above IN>. The residual earth-fault should then be above set IN>. Verify that back-up trip is achieved after set time. If selected, re-trip should also appear. Disconnect AC and START input signals. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 194: Verifying Instantaneous Back-Up Trip At Cb Faulty Condition

    Leave the inputs for CB close inactivated. These signals should not influence. Apply the fault condition, including the start of CCRBRF, with the current above the set IP> value. Check that the re-trip, if selected, and back-up trip commands are achieved. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 195: Completing The Test

    For a short while inject a current (fault current) in one phase to about 110% of the set operating current, and switch the current off. Observe to not exceed the maximum permitted overloading of the current circuits in the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 196: Completing The Test

    No TRIP signal should appear. Reset both BLKDBYAR and EXTPDIND binary inputs. Activate the BLOCK binary input. Activate EXTPDIND binary input. NO TRIP signal should appear. Reset both BLOCK and EXTPDIND binary inputs. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 197: Completing The Test

    During the test, the analog outputs of active and reactive power shall be monitored. Connect the test set for injection of voltage and current corresponding to the mode to be used in the application. If a three-phase test set is available this Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 198 Change the angle between the injected current and voltage to Angle1 + 90°. Check that the monitored active power is equal to 0% of rated power and that the reactive power is equal to 100% of rated power. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 199: Completing The Test

    Increase the current slowly from 0 until the START1 signal, start of stage 1, is activated. Check the injected power and compare it to the set value Power1, power setting for stage 1 in % of Sbase. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 200: Completing The Test

    SEMOD175021-42 v4 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 201: Capacitor Bank Protection Cbpgapc

    Note that during testing the overcurrent feature the harmonic voltage overload feature or reactive power overload feature may also give start and operate signals depending on their actual settings. Therefore it is best to switch them off during this test. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 202 Check that all above mentioned function binary output signals now have logical value zero because they will be automatically blocked by operation of built-in reconnection inhibit feature. Repeat above steps 1-8 for phase L2 and phase L3. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 203 The following formula can be used to calculate SCB reactive power in per-unit system when current with different frequency from the rated frequency is injected. × Q pu rated injected (Equation 89) EQUATION2273 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 204 10. Repeat above steps 1 - 8 to test different points from the above table. Operation of this feature is based on internally calculated peak RMS voltage value. That means that this feature is also able to operate for current signals with varying Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 205: Completing The Test

    Thus, if only the inverse time delay is required, it is important to set the definite time delay for that stage to zero. 11.5.15.1 Verifying settings by secondary injection GUID-EB788169-532A-4A3E-BBEC-DCB28169DF86 v6 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 206     This means that if current jumps from 0 to 2 times start and negative sequence capability value of generator K1 is set to 10 s and current start level Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 207: Completing The Test

    General and make sure that the function is enabled, that is, Operation is set to On. The test of the function may be performed by injecting restrain voltage and increasing the injected current(s). Note the value at which the START and STOC signals are set. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 208 UL2: Ampl = 10 / √3; Angle = 240° • UL3: Ampl = 100 / √3; Angle = 120° Second section of the characteristic only: If VDepMode = Slope, the minimum measured phase-to-phase voltage is between 0,25*UBase and UHighLimit/100*UBase: Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 209 This means that if the measured phase current jumps from 0 to 2 times the set operate level and time multiplier k is set to 1.0 s (default value), then the TROC and TRIP signals will operate after a time delay equal to 13.5 s ± tolerance. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 210 19. Measure the definite time delay for the TRUV and TRIP signals and compare it with the set value tDef_UV. 20. Check that start and operate information is stored in the event menu. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 211: Completing The Test

    Instantaneously decrease the voltage in one phase to a value about 20% lower than the measured operate value. Measure the time delay for the TRIP signal, and compare it with the set value. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 212: Completing The Test

    Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.6.2.1 Verifying the settings M13806-9 v2 Verification of single-phase voltage and time delay to operate for Step 1 M13806-50 v9 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 213: Extended Testing

    Off. Restore connections and settings to their original values, if they were changed for testing purposes. 11.6.3 Two step residual overvoltage protection ROV2PTOV SEMOD54358-3 v7 Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 214: Verifying The Settings

    Off. Restore connections and settings to their original values, if they were changed for testing purposes. 11.6.4 Overexcitation protection OEXPVPH M6583-45 v5 Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.6.4.1 Verifying the settings M6583-49 v4 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 215: Completing The Test

    Prepare the IED for verification of settings as outlined in section "Requirements" and section "Preparing for test" in this chapter. 11.6.5.1 Check of undervoltage levels SEMOD175258-71 v2 This test is relevant if the setting BlkDiffAtULow = Yes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 216 Check U1 blocking level by comparing the voltage level at reset with the set undervoltage blocking U1Low. Repeat steps to check U1Low for the other phases. The connections to U1 must be shifted to test another phase. (UL1 to UL2, UL2 to UL3, UL3 to UL1) Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 217: Check Of Voltage Differential Trip And Alarm Levels

    Check U2 blocking level by comparing the voltage level at reset with the set undervoltage blocking U2Low. 11.6.5.2 Check of voltage differential trip and alarm levels SEMOD175258-104 v3 Procedure Connect voltages to the IED according to valid connection diagram and figure 50. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 218: Check Of Trip And Trip Reset Timers

    Observe that the connections to U1 must be shifted to test another phase. (UL1 to UL2, UL2 to UL3, UL3 to UL1) 11.6.5.3 Check of trip and trip reset timers SEMOD175258-124 v2 Procdure Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 219: Final Adjustment Of Compensation For Vt Ratio Differences

    Loss of voltage check LOVPTUV SEMOD175023-3 v5 Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.6.6.1 Measuring the operate limit of set values SEMOD175023-7 v7 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 220: Completing The Test

    Prepare the IED for verification of settings outlined in Section "Preparing the IED to verify settings". 11.7.1.1 Verifying the settings M16289-15 v3 Verification of START value and time delay to operate M16289-17 v7 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 221 Slowly decrease the frequency of the applied voltage, to a value below StartFrequency. Check that the START signal does not appear. Wait for a time corresponding to tDelay, make sure that the TRIP signal does not appear. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 222: Completing The Test

    Supply the IED with three-phase voltages at their rated values. Slowly decrease the magnitude of the applied voltage, until the BLKDMAGN signal appears. Note the voltage magnitude value and compare it with the set value. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 223: Completing The Test

    The test above can be repeated to check a positive setting of StartFreqGrad. The tests above can be repeated to check the time to reset. The tests above can be repeated to test the RESTORE signal, when the frequency recovers from a low value. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 224: Completing The Test

    Decrease the current slowly and check the reset value. Block high set stage if the injection current will activate the high set stage when testing the low set stage according to below. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 225: Overcurrent Feature With Current Restraint

    Operate time measurement Definite times may be tested as above (non-directional overcurrent feature). For inverse time characteristics the START value (to which the overcurrent Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 226: Overcurrent Feature With Directionality

    Inject voltage(s) in a way that relevant measured (according to setting parameter VoltageInput) voltages are created from the test set. Overall check in principal as above (non-directional overcurrent feature) and correspondingly for the undervoltage feature. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 227: Completing The Test

    The verification is divided in two main parts. The first part is common to all fuse failure supervision options, and checks that binary inputs and outputs operate as expected according to actual configuration. In the second part the relevant set operate values are measured. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 228: Checking That The Binary Inputs And Outputs Operate As Expected

    Signal BLKU after about 50ms • Signal BLKZ after about 200ms 11.9.2.2 Measuring the operate value for the negative sequence function M1405-46 v12 Measure the operate value for the negative sequence function, if included in the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 229 = × 0, 5 IECEQUATION00022 V2 EN-US Compare the result with the set value of the negative-sequence operating current. Consider that the set value 3I2< is in percentage of the base current IBase. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 230: Measuring The Operate Value For The Zero-Sequence Function

    This is the point at which the dead line condition is detected. Check the value of the decreased voltage with the set value UDLD< (UDLD< is in percentage of the base voltage UBase). Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 231: Checking The Operation Of The Du/Dt And Di/Dt Based Function

    STDU or STDI are activated. 10. Check that the start output signals for the current and voltage phases 2 and 3 are activated by changing the magnitude of the voltage and current for phases 2 and 3. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 232: Completing The Test

    USealIn level. MAINFUF signal should not reset. Slowly increase measured voltage to the value slightly above USealIn until MAINFUF signal resets. Record the measured voltage and compare with the set value USealIn. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 233: Completing The Test

    This description describes the test of the version intended for one bay. Figure shows the general test connection for a 1½ breaker diameter with one- phase voltage connected to the line side. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 234 U3PLN2 L12,L23,L31 UMeasure Ph/N U-Line1 Ph/Ph U3PLN1 Input Phase L1,L2,L3 L12,L23,L31 IEC05000481-5-en.vsd IEC05000481 V5 EN-US Figure 52: General test connection for a 1½ breaker diameter with one-phase voltage connected to the line side Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 235: Testing The Synchronizing Function

    During the test of SESRSYN for a single bay arrangement, these voltage inputs are used: U-Line UL1, UL2 or UL3 line 1 voltage input on the IED according to the connection in SMT U-Bus Bus voltage input on the IED according to the connection in SMT Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 236 ± dφ degrees, the user can check that the two outputs are activated for a phase difference lower than the set value. It should not operate for other values. See figure 53. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 237 If a modern test set is used, the frequency can be changed continuously. Testing the reference voltage M2377-249 v5 Use the same basic test connection as in figure 51. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 238: Testing The Energizing Check

    The test should verify that the energizing check function operates for a low voltage on the U-Bus and for a high voltage on the U-Line. This corresponds to an energizing of a dead bus to a live line. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 239: Testing The Voltage Selection

    This test should verify that the correct voltage is selected for the measurement in the SESRSYN function used in a double-bus arrangement. Apply a single-phase voltage of 100% GblBaseSelLine to the U-Line and a single-phase voltage of 100% GblBaseSelBus to the U-Bus. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 240 IED SESRSYN 1 1 ½ bus WA1 – LINE1_Q B1SEL, (Operates on LINE1 LN1SEL WA1_QA1) WA1 – TIE_QA1 LINE2_Q B1SEL, LINE2 LN2SEL WA1 – TIE_QA1 WA2_QA B1SEL, B2SEL Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 241: Completing The Test

    M2377-1042 v5 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 242: Apparatus Control Apc

    Before starting any test, verify the following settings in PCM600 or the local HMI for TR1ATCC, TR8ATCC and TCMYLTC and TCLYLTC. • Confirm power system base quantities I1Base, I2Base, UBase. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 243 It is important to review these settings and confirm the intended response of the voltage control function for different secondary injection tests. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 244: Secondary Test

    This command sequence will be repeated until U brought back within the inner deadband range. 11.10.3.2 Check the activation of the voltage control operation SEMOD175185-537 v8 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 245: Check The Normal Voltage Regulation Function

    Detection of this command will involve locating the allocated binary output for a raise pulse command in the Signal Matrix in PCM600 and monitoring a positive from this output. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 246: Check The Undervoltage Block Function

    Increase the applied voltage slightly above the Umax value and check for the corresponding blocking or alarm condition on the local HMI. For an alarm condition, the voltage regulation function is not blocked and a lower command should be issued from the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 247: Check The Overcurrent Block Function

    When all secondary phase-to-earth voltages are available, use the positive- sequence components of voltage and current. By separation of real and imaginary parts: × × ul re ub re rline il re xline il im (Equation 108) EQUATION2082 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 248: Parallel Voltage Regulation

    For the transformers connected in the parallel group, confirm that OperationPAR is set to MF. For parallel operation, it is also recommended to confirm for parallel group membership, defined by setting TnRXOP in the local HMI under Main menu/Settings/Setting group N/Control/ TransformerVoltageControl(ATCC,90)/TR8ATCC:x/ParCtrl Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 249 Setting confirmation through secondary injection requires calculation of circulating currents for each transformer based on impedance values and respective compensating factors, and is therefore more complex for greater than two transformers. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 250 Circuit Impedance). Using these setting values and the measured quantity of circulating current from the local HMI (Icc_i), calculate the value for circulating current voltage adjustment Uci. × × Ci Icc i Xi (Equation 111) EQUATION2088 V1 EN-US Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 251 Transformer 1. Magnitude and direction of circulating currents measured for each transformer can be observed as service values on the local HMI and raise/lower commands detected from the binary output mapped in the Signal Matrix. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 252 TR8ATCC for all transformers connected in the parallel group, which can be confirmed through interrogation of the local HMI. Confirm that the automatic voltage control for tap changer, parallel control function TR8ATCC responds in accordance with the setting for CircCurrBk. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 253: Completing The Test

    Activation of the different zones verifies that the CS signal is issued from the intended zones. The CS signal from the independent tripping zone must have a tSendMin minimum time. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 254: Testing Permissive Underreaching

    Check that trip time complies with the zone timers and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated. 11.11.1.3 Testing blocking scheme M13868-50 v5 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 255: Testing Delta Blocking Scheme

    11.11.1.5 Checking of unblocking logic M13868-72 v4 Check the unblocking function (if the function is required) when checking the communication scheme. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 256: Completing The Test

    Deactivate the receive (CRLx) signal in the IED. Check that the trip time complies with the zone timers and that correct trip outputs, external signals, and indications are obtained for the actual type of fault generated. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 257: Testing Permissive Overreaching

    M13868-84 v6 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 258: Current Reversal And Weak-End Infeed Logic For Distance Protection 3-Phase Zcrwpsch

    WEIBLK2. Check that correct trip outputs and external signals are obtained for the type of fault generated. The operation time should be about the tDelayRev setting Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 259: Weak End Infeed Logic

    M14947-105 v5 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 260: Scheme Communication Logic For Residual Overcurrent Protection Ecpsch

    Reset the CR binary input. 10. Activate the BLOCK digital input. 11. Switch the fault current on (110% of the set operating current) and wait for a period longer than the set value tCoord. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 261: Completing The Test

    Current reversal and weak-end infeed logic for residual overcurrent protection ECRWPSCH M13936-2 v8 Prepare the IED for verification of settings as outlined in section "Requirements" and section "Preparing for test" in this chapter. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 262: Testing The Current Reversal Logic

    (IN>Dir). Activate the CRL binary input. No ECHO and CS should appear. Abruptly reverse the current to the setting of AngleRCA setup lagging the voltage, to operate the forward directional element. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 263 (180°- AnglRCA) setting, the current leads the voltage. 11. Inject current in one phase to about 110% of the set operate current (IN>Dir ). 12. Activate the CRL binary input. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 264: Completing The Test

    SMBRREC. The function must issue a three-phase trip in all cases when trip is initiated by any protection or some other built-in or external Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 265: 1Ph/3Ph Operating Mode

    (default setting 2.0s) and shorter than the dead- time of SMBRREC, when included in the protection scheme. Check that the second trip is a three-phase trip and that a three-phase autoreclosing attempt is given after the three-phase dead time. Functional Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 266: 1Ph/2Ph/3Ph Operating Mode

    Check that the second trip is a three-phase trip and that a three-phase autoreclosing attempt is given after the three-phase dead time. Functional outputs TRIP, TRLn and TR1P should be active during first fault. No other Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 267: Circuit Breaker Lockout

    SEMOD54375-203 v6 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 268: Monitoring

    ALARM and LOCKOUT disappear. Reset the BLOCK binary input. Make sure that pressure lockout condition exists and then activate the reset lock out input RESETLO and check that the outputs PRESLO and LOCKOUT reset. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 269: Testing The Gas Medium Supervision For Temperature Alarm And Temperature Lock Out Conditions

    LevelAlmLimit or activate binary input signal SENLVLALM, check that outputs LVLALM and ALARM are activated after a set time delay of tLevelAlarm. Liquid level lockout input SENLVLLO can be used to set LVLLO. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 270: Testing The Liquid Medium Supervision For Temperature Alarm And Temperature Lock Out Conditions

    The Signal Monitoring tool in PCM600 shows the service values that are available on the Local HMI as well. Values of the logical signals belong to the breaker monitoring are available on the local HMI under: Main menu/Test/Function status/Monitoring/ BreakerMonitoring/SSCBR:x Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 271: Verifying The Settings

    Check that the output CBLIFEPH is decreased with a value that corresponds to the injected current. 6.4. CBLIFEAL is activated as soon as CBLIFEPH is below the set CBLifeAlmLevel value. Test of accumulated energy Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 272: Completing The Test

    GUID-0A16206F-690E-46EF-86F4-5A89E0BF640B v3 Continue to test another function or end the test by changing the Test mode setting to Off. Restore connections and settings to their original values if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 273: Event Function Event

    £ (X0 + 2 · X1 XM)/3 For single-phase fault with mutual zero-sequence current Test angle Impedance angle ZF • ZF arctan[(X0 + 2 · X1) / (R0 + 2R1)] For single-phase faults • ZF arctan(X1/R1) For two-phase faults Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 274: Measuring The Operate Limit

    Normally the counter will be tested when testing the function that the counter is connected to, such as the trip function. When the function is configured, test it together with the function that operates it. Trigger Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 275: Completing The Test

    Make sure that the WARNINGx and ALARMx signals remains low. Supply three-phase currents slightly more than the rated value to the IED and take note of hot spot temperature (HPTMPMAX). Observe the maximum permitted overloading of the current circuits in the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 276 Note the hot spot temperature (HPTMPMAX) and maintain it for another 1 hour. Check the LOLINDAY and LOLINYRS outputs after 1 hour and compare it with the calculated loss of life value using IEC standard method. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 277: Completing The Test

    Similarly check after each 1 minute whether the calculated integrated energy value and EAFACC and ERFACC outputs are matching. After some time (multiple of minute) remove the current and voltage input from CVMMXN function block. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 278: Completing The Test

    M13906-301 v5 Continue to test another function or end the test by changing the TESTMODE setting to Off. Restore connections and settings to their original values, if they were changed for testing purposes. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 279: Station Communication

    HMI under • Self-supervision status: Main menu/Diagnostics/Internal events • Status for inputs and outputs: Main menu/Test/Function status, browse to the function group of interest. • Remote communication related signals: Main menu/Test/Function status/ Communication/Remote communication Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 280: Basic Ied Functions

    Verifying the settings M11369-4 v4 Check the configuration of binary inputs that control the selection of the active setting group. Browse to the ActiveGroup menu to achieve information about the active setting group. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 281: Completing The Test

    Navigate to the test mode folder. Change the On setting to Off. Press the 'E' key and the left arrow key. Answer YES, press the 'E' key and exit the menus. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 283: Section 12 Primary Injection Testing

    (if resistive or inductive load current is applied) than the Uset voltage and ATCC increases the voltage in order to achieve the correct system voltage at the load point. Confirm the PST settings for Rline and Xline. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 284 Incorrect current polarity may be an issue with physical wiring or the current direction convention selected for the CT analogue input as part of the setting in the PST setting. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 285: Voltage Control Of Parallel Transformers

    Check the overcurrent blocking level (Iblock) in Main menu/Settings/ General settings/Control/TransformerVoltageControl(ATCC,90)/ TR8ATCC:x/TCCtrl/Iblock. Check that the circulating current blocking (OperCCBlock) is set On, and the check the correct settings for circulating current limit (CircCurLimit) in Main menu/Settings/General settings/Control/ TransformerVoltageControl(ATCC,90)/TR8ATCC:x/ParCtrl/ CircCurrLimit. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 286 T2 and T3. The currents measured at T2 and T3 will ideally be about the same values. If the voltage is close to the upper limit of the UDeadband, the tap changer of T1 will try to decrease Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 287: Master Follower (Mf) Method

    Set the control mode to Manual for each transformer in the parallel control group Open the test display for Transformer Voltage Control on the LHMI in Main menu/Test/Function status/Control/TransformerVoltageControl (ATCC, 90). Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 288: Completing The Test

    After the test is completed and relevant disturbance records are saved to document the test, go to Main menu/Clear on the local HMI and clear all LEDs, the process eventlist and disturbances from the IED. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 289: Section 13 Checking The Directionality

    ZDMRDIR are available under the HMI menu: Main menu/ Settings/IED Settings/Impedance protection/ DirectionalImpedance The primary load impedance must have an angle (PHI) between the setting angles for the directional lines. In case of default settings this means: Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 290 Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 291 (importing) resistive load (active power). Usually it is enough to look at the resistive values to get information of the load direction, that must anyway be compared with the indication given by external equipment measuring the same power flow. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 293: Section 14 Commissioning And Maintenance Of The Fault Clearing System

    The periodicity of all tests depends on several factors, for example the importance of the installation, environmental conditions, simple or complex equipment, static or electromechanical IEDs, and so on. The normal maintenance praxis of the user should be followed. However, ABB's recommendation is as follows: Every second to third year •...
  • Page 294: Visual Inspection

    IED at a time on live circuits where redundant protection is installed and de-energization of the primary circuit is not allowed. ABB protection IEDs are preferably tested by aid of components from the COMBITEST testing system described in information B03-9510 E. Main...
  • Page 295: Recording

    When the protection IED undergoes an operational check, a tripping pulse is normally obtained on one or more of the output contacts and preferably on the test switch. The healthy circuit is of utmost importance for the protection operation. If Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 296: Measurement Of Service Currents

    The neutral-point voltage to an earth-fault protection IED is checked. The voltage is normally 0.1 to 1V secondary. However, voltage can be considerably higher due to harmonics. Normally a CVT secondary can have around 2.5 - 3% third-harmonic voltage. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 297: Restoring

    Thus a list should be prepared of all items disturbed during test so that all can be put back into service quickly and without overlooking something. It should be put back into service item by item and signed by the responsible engineer. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 299: Section 15 Troubleshooting

    No problem detected. None. Time synch Fail No time synchronization. Check the synchronization source for problems. If the problem persists, contact your ABB representative for service. Real time clock Ready No problem detected. None. Real time clock Fail The real time clock has Set the clock.
  • Page 300: Fault Tracing

    Ready (I/O module name) Fail I/O modules has failed. Check that the I/O module has been configured and connected to the IOP1- block. If the problem persists, contact your ABB representative for service. 15.2 Fault tracing IP8765-1 v1 15.2.1 Internal fault indications...
  • Page 301: Using Front-Connected Pc

    The internal events are time tagged with a resolution of 1ms and stored in a list. The list can store up to 40 events. The list is based on the FIFO principle, when it is Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 302 This means that, when using the PC for fault tracing, it provides information on the: • Module that should be changed. • Sequence of faults, if more than one unit is faulty. • Exact time when the fault occurred. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 303: Diagnosing The Ied Status Via The Lhmi Hint Menu

    3PHSUM block should have the same cycle time as that of Phasor Report. PMU not connected to 3ph output The PMU phasor report input(s) must be connected to the 3ph output of SMAI or 3PHSU. Table continues on next page Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 304 Please restart IED and consider Reconfigure HW modules to get updated hardware list. Non ABB vendor SFP detected Non ABB vendor SFP detected. Corresponding hardware(s) is set to fail. Please use ABB approved SFP’s. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 305: Repair Instruction

    M11764-10 v1 An alternative is to open the IED and send only the faulty circuit board to ABB for repair. When a printed circuit board is sent to ABB, it must always be placed in a metallic, ESD-proof, protection bag.
  • Page 306: Repair Support

    Repair support M11768-3 v3 If an IED needs to be repaired, the whole IED must be removed and sent to an ABB Logistic Center. Before returning the material, an inquiry must be sent to the ABB Logistic Center. e-mail: offer.selog@se.abb.com 15.5...
  • Page 307: Section 16 Glossary

    Binary signal transfer function, receiver blocks Binary signal transfer function, transmit blocks C37.94 IEEE/ANSI protocol used when sending binary signals between IEDs Controller Area Network. ISO standard (ISO 11898) for serial communication Circuit breaker Combined backplane module Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 308 Delayed autoreclosing DARPA Defense Advanced Research Projects Agency (The US developer of the TCP/IP protocol etc.) DBDL Dead bus dead line DBLL Dead bus live line Direct current Data flow control Discrete Fourier transform Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 309 File Transfer Protocol Function type G.703 Electrical and functional description for digital lines used by local telephone companies. Can be transported over balanced and unbalanced lines Communication interface module with carrier of GPS receiver module Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 310 PCI specifications from the PCI SIG (Special Interest Group) for the electrical EMF (Electromotive force). IEEE 1686 Standard for Substation Intelligent Electronic Devices (IEDs) Cyber Security Capabilities Intelligent electronic device IET600 Integrated engineering tool Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 311 LON network tool Local operating network Miniature circuit breaker Mezzanine carrier module Milli-ampere module Main processing module MVAL Value of measurement Multifunction vehicle bus. Standardized serial bus originally developed for use in trains. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 312 Permissive underreach transfer trip RASC Synchrocheck relay, COMBIFLEX Relay characteristic angle RISC Reduced instruction set computer RMS value Root mean square value RS422 A balanced serial interface for the transmission of digital data in point-to-point connections Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 313 Switch or push button to trip Starpoint Neutral point of transformer or generator Static VAr compensation Trip coil Trip circuit supervision Transmission control protocol. The most common transport layer protocol used on Ethernet and the Internet. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 314 Gregorian calendar. It is used for aeroplane and ship navigation, where it is also sometimes known by the military name, "Zulu time." "Zulu" in the phonetic alphabet stands for "Z", which stands for longitude zero. Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 315 A digital signalling interface primarily used for telecom equipment Three times zero-sequence current.Often referred to as the residual or the earth-fault current Three times the zero sequence voltage. Often referred to as the residual voltage or the neutral point voltage Transformer protection RET670 2.2 IEC Commissioning manual...
  • Page 318 — ABB AB Grid Automation Products 721 59 Västerås, Sweden Phone: +46 (0) 21 32 50 00 abb.com/protection-control © Copyright 2017 ABB. All rights reserved. Specifications subject to change without notice.

Table of Contents